New Roof and Solar Together: The Order of Work
The roof goes first and the array second, but the two are planned as one project. The survey and the array design come before the re-roof, so the roofer knows where the array will sit. Then the roof is replaced, the mounts are set into the new covering and flashed, the array and the electrical work go in, the city inspects, and the utility sets the net meter. The paperwork doesn't have to wait for the roof: on our recent Los Angeles jobs the utility application was filed with the permits or while the roof was open, and from roofing permit to permission to operate took 38 days on a 2026 Canoga Park tile roof and 55 days on a 2021 Encino shingle roof. Our jobs show two ways to fit the trades together: finish the roof and then mount the array on it, or interleave them, with the roofer laying the field, the solar crew setting the array and the roofer coming back to close the covering around it. This page sets out the order as of October 2026.

Whether the roof needs replacing before solar at all is covered in should you replace your roof before solar, and taking an existing array off and putting it back is in solar removal and reinstall for a re-roof.
The order of work
Each step has an owner, and the handoffs between the roofer and the solar crew are where a combined job goes right or wrong.
| Step | What happens | Who |
|---|---|---|
| 1. Survey | The roof measured plane by plane, the deck and layers checked, the electrical service looked at | The roofer and the solar designer |
| 2. Design | The array laid out on the roof as it will be, around vents, chimneys and setbacks; the footprint given to the roofer | The solar designer |
| 3. Permits | A re-roof permit, a solar permit, and a service panel permit if the panel is replaced | The contractor for each scope |
| 4. Utility application | The interconnection application filed; it can run while the roof is done | The solar contractor |
| 5. Re-roof | Tear-off, deck check and repairs, underlayment, flashing and covering, with the roof's own inspections | A roofing contractor (C-39) |
| 6. Mounts | Attachments into the rafters, each flashed into the new covering | The solar crew, or the roofer |
| 7. Array and electrical | Racking, modules, inverters or microinverters, conduit and any panel work | A solar (C-46) or electrical (C-10) contractor |
| 8. City final | The city inspects the solar and electrical work and releases it to the utility | The contractor schedules it |
| 9. Utility | Meter set and permission to operate | The utility, such as LADWP or SCE |
How the re-roof itself runs, step by step, is in the roof replacement process, and how a mount is sealed against leaks in solar mount flashing.
Two ways to fit the roofer and the solar crew together
Roof finished first. The re-roof runs to its final inspection, and then the mounts go into the new covering. On our 2021 Canoga Park job, 42 squares of shingle, the roofing permit was finaled 12 days after it was issued, the solar and service panel permits were paid two days later, and all three permits closed within five weeks of the roofing permit. On a 2021 Encino house, we fixed each standoff to a rafter with its flashing tucked under the shingle course above, so every penetration was a roofing detail.
Interleaved. On a 2022 Granada Hills house, with the roof done by another contractor, the roofer laid the field of the covering in one day, we installed the array, and the roofer came back for a day to close the covering around the mounts. To plan that second visit, the roofer asked how many square feet the array would cover: about 425. Two trades, three visits, one covering.
Either way, agree the order before anyone starts, in writing, along with who flashes the mounts.
Tile roofs. Tile that comes off can go back around the array. On a 2026 Chatsworth house, we stripped the tile from 17 squares, laid synthetic underlayment and composition shingle across that field in a color matched to the tile from a cool-roof approved line, put the original clay tile back around it and set the array on the shingle. On a 2026 Canoga Park house, every tile came off, new underlayment went down, the same tile went back and the array followed. The choices for an old tile roof are compared in repair, relay or new tile.
Permits and inspections in Los Angeles
In the City of Los Angeles, both scopes can go through express permits, without plan check, when they fit the limits of LADBS Information Bulletin P/GI 2026-003 (revised June 10, 2026):
- The re-roof. An express permit covers a Class A or B covering weighing less than 6 pounds per square foot over solid sheathing. Class A is required in a Very High Fire Hazard Severity Zone, and replacing more than 50% of a house's roof calls for a cool roof product certified by the Cool Roof Rating Council. Panels over the roof don't relieve it of that rule; see the cool-roof rule on a re-roof.
- The solar. Express solar permits are issued online, to contractors only, for rooftop systems on one- or two-family houses of 10 kW or less with a service panel rated 225 amps or less, among other limits; a separate building permit may be needed for the structural support. A system outside those limits goes through plan check; our 2023 Woodland Hills job, with a backup subpanel, had city plan-check corrections in May and the city's final release on June 21.
- The service panel. If the panel is replaced to give the array a place to connect, it has its own permit; on the 2021 Canoga Park job it was a new panel with a 200-amp main breaker.
Outside the city, each building department sets its own permits; how the agencies in Los Angeles County handle a re-roof is in re-roof permits in Los Angeles County by city.
The utility's side
With LADWP, our jobs have run through these steps: the interconnection application, the utility's review, a site evaluation and permission to install, the city's final release posted to the utility, a field order for the meter, and the net meter set, which is permission to operate.
File it early. On the 2026 Canoga Park tile job we filed the application while the roof was open, so the two calendars ran together instead of end to end: roofing permit February 10, application February 21, building department release March 5, permission to operate March 20. On the 2026 Chatsworth job the application was filed the same day the express permit was issued, January 6, and the net meter was set February 18.
Tell the utility what the re-roof changed. On our 2023 Woodland Hills job, the utility's photo review raised a clearance objection to a structure that was no longer there after the re-roof; we explained what had changed on site, and it was accepted the same day.
Who does what, and who answers for the mounts
The roof is roofing work, under the C-39 classification; the solar is the work of a C-46 solar or C-10 electrical contractor, according to the Contractors State License Board's descriptions of the classifications. One contractor holding both can carry the whole job; with two, each works under its own license, and the handoffs need to be written down:
- the order of work and each trade's dates;
- who pulls which permit and who files with the utility;
- the array footprint and the mount layout, before the roofer orders material;
- who flashes the mounts, and with what;
- who answers for a leak at a mount, in writing.
That last point matters because the shingle maker doesn't warrant the solar installation. Owens Corning's Preferred Protection warranty, in its August 2026 version, excludes damage caused by alterations after the roof is installed, solar panel installation among them, and GAF's position is in roof, solar and installer warranties. On the 2026 Chatsworth job, we confirmed in writing that the roof penetrations are covered by our workmanship warranty.
Our roof-and-solar jobs
Each of these put the roof and the array on one calendar.
| Job | Roof | Order | Calendar |
|---|---|---|---|
| Encino, 2021 | 20 squares of Class A shingle; roof and solar by us | Roof first, then standoffs and the array | Roofing permit September 16, permission to operate November 10: 55 days |
| Canoga Park, 2021 | 42 squares of shingle and a new 200-amp panel; all by us | Roof finaled, then the solar and panel permits | Three permits closed within five weeks |
| Granada Hills, 2022 | Roof replaced under and around the array by another roofer; solar by us | Interleaved: field, array, then the covering closed around the mounts | May to June 2022 |
| Chatsworth, 2026 | Tile off 17 squares, shingle under the array, tile back around it; all by us | Permit and utility application the same day, then roof and array | January 6 to the net meter February 18: 43 days |
| Canoga Park, 2026 | 26 squares of tile reset on new underlayment; all by us | Roof, with the utility application filed while it was open, then the array | Roofing permit February 10, permission to operate March 20: 38 days |
Other jobs are in our project write-ups; how long the roof part takes is in how long a roof replacement takes. Our California contractor license, CSLB #1032379, carries the C-39 roofing classification alongside B and C-10.
Frequently asked
Should the roof or the solar go first?
Can one company do the new roof and the solar?
How long does a new roof and solar take together?
Do I need separate permits for the roof and the solar?
Who's responsible if the roof leaks at a solar mount?
Related reading
Sources & methodology
Code sections, rules and figures on this page come from the primary sources below. Codes, local requirements and product terms change; each was verified October 9, 2026.
- Los Angeles Department of Building and Safety, Express Permits (No Plan Check Required), Information Bulletin P/GI 2026-003, effective January 1,…
- Contractors State License Board, Description of Classifications (C-10 Electrical, C-39 Roofing, C-46 Solar)
- Owens Corning, Preferred Protection Limited Lifetime Warranty (Pub. No. 10020609-P, August 2026)
We do the roof and the solar as one job
Call (323) 844-7777. We hold the roofing (C-39) and electrical (C-10) classifications, so one schedule covers the survey, the re-roof, the array and the utility paperwork. Have ready the address, photos of the roof and a recent electric bill.
Prepared by Cali Energy, October 9, 2026. This article is for general educational purposes only and is not legal, tax, financial, engineering, or utility advice. Rates, incentives, codes, permit requirements, equipment specifications, prices, and program terms may change; figures and timelines are estimates, not guarantees. Confirm current requirements with the applicable utility, AHJ, program administrator, manufacturer, or a licensed professional. See our Content Disclaimer. Cali Energy · 19201 Parthenia St, Unit E, Northridge, CA 91324 · CSLB #1032379 (B, C-10, C-39)