Cali Energy research · Public permit records

Residential Solar Permits in Unincorporated LA County: 36,175 EPIC-LA Records, 2020–2026

In unincorporated Los Angeles County, applications for new rooftop solar on existing homes fell from 8,401 in 2022 to 3,841 in 2025 (−54%), and January–August 2026 is running 32% below the same months of 2025. Over the same years the share of new systems filed with a battery rose from 7% to 64%. Since August 2023 most systems go through the county’s Express path, where 86–91% of permits are issued the same day. Source: 36,175 residential solar permit records in LA County Public Works’ EPIC-LA system, January 2020 – August 2026.

Updated October 7, 2026 · Data through August 2026 · Cali Energy research team · CSLB #1032379 · verify license

−54%
New-system applications, 2022 → 2025 (8,401 → 3,841)
64%
Of 2025 new-system applications include a battery (7% in 2022)
86–91%
Of Express permits issued the same day they were filed
14–19%
Of permits issued for 2020–2023 filings still show no final inspection

Coverage. EPIC-LA is the permit system of LA County Public Works. This study uses its records for unincorporated county areas — communities without their own city government, such as Altadena, East Los Angeles, Hacienda Heights, Rowland Heights, Stevenson Ranch, Castaic, Quartz Hill, Acton and Topanga. The City of Los Angeles (LADBS) and cities with their own building departments are not included; for the City of LA see LADBS solar permits. Counts are permit applications by month filed, not finished installations.

Solar permit applications month by month

New systems on existing homes, unincorporated LA County. Dark part: filed with a battery.

New rooftop solar applications per month, with and without a battery
Filed with a batterySolar only
Monthly residential solar permit applications in unincorporated LA County, 2020 to August 2026Peaks of about 1,051 a month in spring 2022, a smaller rush in March and April 2023, then a steady decline to about 236 a month in 2026, with batteries in most filings from 2024.02004006008001,0001,2002020202120222023202420252026Net billing starts, Apr 2023Express path opens, Aug 202325D tax credit ends, Dec 2025
Applications by month filed. A battery is counted when the permit is in the Express “with ESS” category or the description mentions a battery or energy storage; before August 2023 this undercounts batteries filed on a separate electrical permit.

Three moments stand out. In March and April 2023 applications rose to 858 and 809, up from 475 in January, just before SCE customers’ new interconnection applications moved from net metering (NEM 2.0) to the Net Billing Tariff on April 15, 2023 (NEM 3.0 explained); most of unincorporated LA County is SCE territory. In late August 2023 the county opened its Express path for standard residential systems, with and without storage, close to the September 30, 2023 deadline in California’s SB 379 for automated solar permitting (California Energy Commission). And there was no rush before the federal 25D credit ended: July–December 2025 averaged 288 applications a month against 353 in January–June, because the credit required a system to be placed in service by December 31, 2025, and a late-2025 permit was usually too late (the 30% credit ended).

The biggest spike, March–April 2022, is not a countywide shift: 58% of those 2,051 filings were in the Santa Clarita Valley (against 23% in the rest of 2022), and one description template accounts for 37% of them (against 5% in the rest of the year) — the signature of a single high-volume program filing in bulk.

Solar permit applications by year and type

New rooftop solar on existing homes: applications per year
Full yearJanuary–August
Yearly applications for new rooftop solar on existing homes, unincorporated LA CountyUp from 2,951 in 2020 to 8,401 in 2022, down to 3,841 in 2025.02,0004,0006,0008,00010,0002,95120205,05520218,40120226,67420235,10820243,84120251,8842026*
Bars: full calendar year (2026*: January–August only). Dashed line: January–August of each year, so 2026 compares like for like.
Residential solar permit applications by year and type, unincorporated LA County
Year filedNew system, existing homeAdded to existing systemNew home or ADURemove & reinstallTotal
20202,951116243,028
20215,0552717685,266
20228,40129231138,674
20236,6742632587,033
20245,10836261715,476
20253,841464511534,491
2026*1,884281721232,207
2026*: January–August. 209 records whose description describes a building, not a solar installation, are excluded (see Methodology).
How to cite: Cali Energy, “Residential Solar Permits in Unincorporated LA County, 2020–2026,” updated October 7, 2026, https://cali-energy.com/research/la-county-solar-permits. Aggregated data are free to use under CC BY 4.0 with a link to this page.

New systems on existing homes are 94% of all records and drive the trend. The other three types move on their own: new homes and ADUs rose from 62 in 2020 to 451 in 2025, since California’s Title 24 code requires solar on most new homes (does a new ADU need solar?); the 2025 rise is concentrated in the San Gabriel Valley and foothills (287 of 451), the region that includes Altadena. Remove-and-reinstall permits went from 4–13 a year to 153 in 2025 — see below. Solar roof tiles and solar shingles (Tesla Solar Roof, GAF Timberline and other building-integrated PV) were 45 applications in 2020 and 13 in 2025, under 2% of new systems in any year (solar roof vs. panels).

How many new solar systems include a battery?

Share of new-system applications filed with a battery
All applicationsStandard path only
Battery share of new rooftop solar applications by year7 percent in 2022, 61 percent in 2024, 64 percent in 2025.0%20%40%60%80%100%9%20208%20217%202219%202361%202464%202556%2026*
Bars: all new-system applications. Dashed line: standard (non-Express) path only, where the way batteries are recorded did not change. 2026*: January–August.
Batteries in new rooftop solar applications
Year filedApplicationsWith a batteryFiled via ExpressBattery share, ExpressBattery share, standard path
20202,9519%——9%
20215,0558%——8%
20228,4017%——7%
20236,67419%17%64%9%
20245,10861%69%74%33%
20253,84164%62%83%33%
2026*1,88456%56%77%29%
2026*: January–August. Express path opened in late August 2023.

Part of the jump is how batteries are recorded: the Express path has a separate “with ESS” category, while standard permits mention a battery only in the description. But the shift shows up on the standard path too, where nothing changed in the recording: 7–9% in 2020–2023, 33% in 2024 and 33% in 2025. On Express, 83% of 2025 filings included storage. Under net billing, solar exported at midday earns far less than power used in the evening, so storing it pays more — see do I need a battery with NEM 3.0 and what NEM 3.0 did to California solar.

How long does a solar permit take in LA County?

New systems on existing homes, by year filed.

Days from application to permit, and from permit to final inspection
Path, year filedPermits issuedMedian days to permitIssued same dayMedian days, permit to final
Standard 20202,580212%44
Standard 20214,5951414%70
Standard 20227,7291413%85
Standard 20234,755124%112
Standard 20241,04457%179
Standard 20251,09543%—
Standard 2026*621210%—
Express 20231,117091%126
Express 20243,442087%106
Express 20252,308087%—
Express 2026*1,020086%—
Permit to final: only permits that reached final inspection. Not shown for 2025–2026 filings, many of which are still open, so a median of those already finaled would be too short.

On Express, the permit is issued at filing: 86–91% the same day, median 0 days. On the standard path the median wait fell from 21 days in 2020 and 14 in 2022 to 4 in 2025 and 2 so far in 2026. The permit is no longer the slow step. From permit to final inspection the median was 106 days for 2024 Express filings and 179 for standard ones; that span includes installation, any main panel or utility work and scheduling the inspection, not county review alone. For the full sequence through utility approval, see permit to PTO timeline in Los Angeles.

How many solar permits reach final inspection?

Status in September 2026 of new-system applications, by year filed.

What happened to residential solar permit applications
Year filedApplicationsPermit issuedFinaledIssued, no final on recordVoid, canceled or expiredOther open status
20202,95187%67%14%14%5%
20215,05591%73%13%14%0%
20228,40192%74%14%8%5%
20236,67488%66%17%13%4%
20245,10888%57%23%16%5%
20253,84189%60%23%11%6%
Shares of applications filed that year. As a share of permits issued, “issued, no final” is 14–19% for 2020–2023 filings. Other open status: in review, approved pending clearances, on hold or waiting for the applicant. 2026 is too recent to judge and is in the CSV only.

Nine in ten applications get a permit, and 8–16% are voided, canceled or left to expire. The notable group is the permits that were issued and never closed: for applications filed in 2020–2023, 14–19% of issued permits still show “Issued” with no final inspection in the county record years later. Some are systems that were installed but whose final inspection was never requested or recorded; some were never built. The record alone cannot tell which. An open permit can come up when a home is sold or refinanced, so if your system is a few years old, look it up on EPIC-LA: it should say Finaled. Common reasons a final fails are covered in why solar inspections fail.

Remove-and-reinstall permits for re-roofs

Permits to take an existing array off and put it back, almost always for a new roof, were 4–13 a year in 2020–2023, then 71 in 2024, 153 in 2025 and 123 in January–August 2026. 73% of the 2025 permits mention the re-roof, and the number citing a linked building permit rose from 2 in 2024 to 22 in 2025 and 33 in January–August 2026. The record cannot show whether more homeowners are re-roofing under solar or whether more of these jobs are now permitted separately; either way, a re-roof under existing panels is a permitted solar job. See solar removal and reinstall for a roof replacement.

Where solar is being permitted

New systems on existing homes by region, 2022–2025.

New rooftop solar applications by region, unincorporated LA County
Region20222023202420252022 → 2025
Santa Clarita Valley2,6421,466956913−65%
San Gabriel Valley & foothills2,5382,4231,7191,132−55%
Southeast & South LA County1,9031,5951,3761,042−45%
Antelope Valley1,011898802521−48%
Santa Monica Mountains, coast & Palos Verdes259264219194−25%
Other unincorporated areas48283639−19%
Regions are assigned from the community name in the permit address and cover only unincorporated parts of each region.

Every region fell. The Santa Clarita Valley fell furthest, by 65%, partly because its 2022 total includes the spring 2022 bulk filings. The Santa Monica Mountains, coast and Palos Verdes fell least, by 25%. Since 2023 the San Gabriel Valley and foothills have filed the most new systems of any region.

Methodology

Source
LA County Public Works EPIC-LA case history, public ArcGIS layer (EPIC-LA_Case_History_view), downloaded September 2026. Statuses and dates are as of the download.
Records
Residential rooftop solar cases in unincorporated county areas (case types “Unincorporated Solar” and “Unincorporated Express”; work classes Roof Mount Residential and Express Solar Roof Mount Residential, with and without ESS), applied January 2020 – August 2026: 36,384 records. Earlier years are incomplete in the system and not used. Contract cities that joined EPIC-LA in 2023–2024 are left out so the series stays like for like.
Types
Assigned from each permit’s description by written rules, in this order: remove-and-reinstall (R&R wording; a solar roof installed with a new roof counts as a new system), added to an existing system, new home or ADU (tract, lot, ADU, new construction or Title 24 wording, or a tract project), and new system on an existing home for the rest.
Excluded
209 records whose description is a building scope (for example, “new detached ADU, 2 bed, 2 bath”) with no mention of solar. 67% of them were later voided, against 5% of new-system records, which is consistent with cases opened in the wrong category.
Checked by hand
The rules were refined after reading samples of 30 descriptions per type; in the final samples every remove-and-reinstall, add-on, new-home and new-system record matched its type, apart from a few ADU building descriptions that say only “PV system required”, which are kept as new homes.
Battery
Counted when the permit is in the Express “with ESS” category or its description mentions a battery, energy storage, ESS, Powerwall or a similar product. A battery on a separate electrical permit and not mentioned in the solar permit is missed, so shares before August 2023 are a lower bound.
Timing
Days to permit: application date to issue date. Permit to final: issue date to completion date, for finaled permits only, by year filed. Medians.
Regions
From the community name in the permit address, grouped into five regions; names that don’t match a region go to “Other”. Addresses are used only for this grouping and are not published.
Limits
Applications are not installations: some are never built, and one home can have more than one record. Descriptions are free text written by applicants, so a small share of records may be typed wrongly. The study says nothing about the City of Los Angeles or other cities.

Frequently asked questions

How long does it take to get a solar permit in LA County?

For unincorporated LA County, an Express permit is usually issued the day you apply (86–91% same day since 2023). Standard permits took a median 4 days in 2025, down from 21 in 2020. The final inspection comes after installation, a median of about 106 days after the permit for 2024 Express filings.

How many solar permits does LA County issue each year?

In unincorporated LA County, 8,401 applications for new rooftop solar on existing homes were filed in 2022 and 3,841 in 2025, plus new-home, ADU, add-on and remove-and-reinstall permits (4,491 records in total in 2025).

Did NEM 3.0 reduce solar installations in Los Angeles County?

Applications in unincorporated LA County fell 54% from 2022 to 2025, with a rush in March–April 2023 just before net billing took effect for new SCE applications and a steady decline after it. Permit data show the timing; they don’t isolate one cause.

What share of new solar systems in LA County include a battery?

64% of 2025 new-system applications in unincorporated LA County included a battery, up from 7% in 2022. On the Express path it was 83%.

Does LA County have an express solar permit?

Yes. Since late August 2023 standard residential rooftop systems, with or without battery storage, can go through the county’s Express Solar path in EPIC-LA, where most permits are issued the same day.

Does this data include the City of Los Angeles?

No. The City of Los Angeles issues its own permits through LADBS, and other cities with their own building departments are also outside EPIC-LA’s unincorporated records.

Related guides

More research

Next steps

Planning solar or a battery in Los Angeles County?

Prepared by Cali Energy, October 7, 2026, from LA County Public Works’ public EPIC-LA permit records (statuses as of September 2026). Counts are permit applications, not completed installations; types are assigned from free-text descriptions and may contain small errors. Not legal or permitting advice. See our Content Disclaimer.