Sunland, Los Angeles, CA · May 2024 · LADWP / LADBS

A virtual final, and the inspector could not connect

Nineteen modules on two faces, installed in a day. The final was booked as a video call with the inspector, and on the morning of the inspection the call never connected.

This Sunland installation is 19 modules with Enphase microinverters on two faces of a shingle roof, installed by Cali Energy in one day on 2 May 2024. The final was booked as an LADBS virtual inspection on 9 May; the inspector could not connect to the video call, and Cali Energy requested a replacement appointment that morning. The final was rescheduled for 11 May, and on 13 May LADBS approved the job and sent the electrical service release to LADWP.

Rows of solar modules on a dark shingle roof with neighboring houses and foothills behind, Sunland
The main field of modules, with the foothills behind the neighbors' roofs.

At a glance

Array
19 modules, 13 on one face and 6 on the other
Microinverters
Enphase, one per module
Installed
Thursday 2 May 2024, in one day
Final
LADBS virtual inspection, 9 May; rescheduled to 11 May
Service release to LADWP
13 May 2024

The story

The installation went to plan. The materials were delivered early on Thursday 2 May and the array went on that day: nineteen modules with a microinverter under each, thirteen on one face and six on the other, and the circuit taken down to the wall in conduit labeled as a solar circuit along its run.

Conduit on a shingle roof with a red CAUTION SOLAR CIRCUIT label, Sunland
The roof conduit, labeled as a solar circuit along its run.

The next day one item was left before the final: the ground rods at the service. The final was requested for Thursday 9 May.

A closed junction box on a shingle roof labeled JUNCTION BOX and CAUTION SOLAR CIRCUIT, beside the array, Sunland
The roof junction box, closed and labeled.

LADBS set the final as a virtual inspection. The inspector's invitation came the day before: a video call at 9:30, a participation agreement to sign and return in advance, and the call joined from a phone on site so the inspector could be walked through the job. The signed agreement went back that morning.

At 9:30 on the 9th the inspector could not connect. The inspection did not take place, and Cali Energy requested a replacement appointment the same morning. The final was rescheduled for Saturday 11 May.

An Enphase combiner box mounted on a stucco wall beside the electrical service, Sunland
The Enphase combiner on the wall by the service.

On Monday 13 May LADBS sent its notice: the department had approved the job and sent the electrical service release to LADWP. The notice on this project also said that LADWP needs a residential project initiated on its side, through its small-projects route, within six months of the release. The building department's part was complete; the utility's part is the next step on the way to permission to operate.

How it ran

Thursday 2 May 2024Materials delivered; 19 modules installed
3 May 2024Ground rods the remaining item before the final
8 May 2024Virtual inspection invitation; participation agreement signed and returned
9 May 2024Inspector could not connect; replacement appointment requested for Saturday 11 May
13 May 2024LADBS approves and sends the service release to LADWP

Eleven days from install to service release.

What we did

  • Installed 19 modules with a microinverter under each in one day.
  • Ran the roof circuit in labeled conduit to a labeled junction box.
  • Signed and returned the virtual inspection participation agreement.
  • Requested a replacement appointment the morning the call failed.
  • Took the job through the final to the LADBS service release.

System specifications

Modules19, on two roof faces (13 and 6)
MicroinvertersEnphase, one per module
Roof wiringConduit and junction box labeled as a solar circuit
CombinerEnphase, on the wall at the service
Final inspectionLADBS virtual inspection
Utility / AHJLADWP / LADBS

Is your project like this one?

  • Your solar final has been booked as a virtual inspection.
  • Your inspection did not take place and you want to know what happens next.
  • You have an LADBS service release notice and are not sure what comes after it.
  • You live in Sunland and want to know how the paperwork runs after the install.

Cali Energy in Sunland

Sunland is a neighborhood inside the City of Los Angeles: permits run through LADBS, interconnection through LADWP.

Sunland is part of the City of Los Angeles, and LADBS, the city's building department, runs some inspections as virtual inspections: the inspector joins a video call and the contractor walks the camera through the job.

Frequently asked questions

How did the virtual inspection work on this Sunland project?

LADBS sent an invitation the day before: a video call at a set time, a participation agreement to sign and return first, and the call joined from a phone on site so the inspector could be walked through the installation. On the day, the inspector could not connect, and a new final was requested.

What happened when the virtual inspection did not connect?

The inspection did not take place. Cali Energy requested a replacement appointment that morning, the final was rescheduled for 11 May, two days later, and LADBS issued the service release to LADWP on 13 May.

What did the LADBS service release notice say?

That LADBS had approved the job and sent the electrical service release to LADWP. The notice for this project added that LADWP needs a residential project initiated on its side within six months of the release. At that point the building department's part was done and the utility's part was next.

Does Cali Energy handle LADBS inspections in Sunland?

Yes. Sunland is inside the City of Los Angeles, so solar finals are LADBS inspections, sometimes run virtually, and the grid connection is with LADWP. Cali Energy installs here and meets the final, in person or on a video call. License CSLB #1032379.

What this would look like on your roof

Planning solar in Sunland? Tell us your utility, your roof and what your bill looks like now, and we will model what a system like this would do on your house before you commit to anything.

Or call +1 (323) 844-7777 · Cali Energy, Northridge · CSLB #1032379 (B, C-10, C-39) — design, permits, install and electrical under one licensed contractor.

Related

Updated October 2026.