Northridge, CA · January – April 2021 · LADWP / LADBS

No wire to the house. The service runs underground.

Five point one kilowatts on a two-storey house with an underground service. Permit set in March, permission to operate in April.

Whether a house is fed overhead or underground is recorded on the utility's work request and it shapes the site visit, the meter spot and where the solar connection lands. It does not change what goes on the roof.

Solar array along a shingle roof under heavy cloud, Northridge
The array, on a grey January morning.

At a glance

System
5.1 kW AC-CEC
Service
Underground
Modules
Canadian Solar 320 W
Inverter
SolarEdge HD-Wave
Permit set to PTO
Six weeks
Utility site visit
Required
Utility / AHJ
LADWP / LADBS

The story

The first thing the utility's own work request says about this house is not the system size. It is two letters: UG. The service is underground — no drop from a pole, no wire across the garden, the supply arriving from below.

That matters for the parts of a solar job that happen at ground level. The utility sends someone out to look before it commits to anything, and where the meter sits and how the new connection reaches it are settled on that visit rather than on a drawing.

Roof junction box with bonding conductor on a shingle roof, Northridge
The roof junction box and the bonding into it.

On the roof it changes nothing. Canadian Solar 320 watt modules in a long run down the main slope, a SolarEdge HD-Wave inverter on the wall, and a junction box on the roof where the array wiring is collected and bonded before it goes down the conduit.

String inverter mounted on a stucco wall with conduit, Northridge
The inverter, on the wall by the service.

The calendar was short. Two proposals in early January, the permit set received in the second week of March, the utility's site visit two weeks later, the first four progress notices in a single day on the twenty-fifth, the installation released on the fifth of April and permission to operate on the twentieth. Six weeks from permit set to switch-on.

Two-storey house with a solar array on the roof seen from the garden, Northridge
From the garden, the whole job.

On this house the underground service meant the same roof work, a site visit from the utility and a meter spot settled on the ground rather than on a drawing. Whether yours is handled the same way depends on what the utility finds when it looks.

How it ran

5 January 2021Two proposals issued
10 March 2021Permit set received; interconnection request filed
23 March 2021Utility site visit required and attended
25 March 2021Four progress notices; solar site evaluation complete
5 April 2021Solar service installation released
20 April 2021Permission to operate — 5.1 kW AC-CEC

Six weeks from permit set to permission to operate.

What we did

  • Issued two proposals before the design was fixed.
  • Filed the interconnection request the same week the permit set arrived.
  • Attended the utility's required site visit on an underground-served house.
  • Installed Canadian Solar 320 watt modules with a SolarEdge HD-Wave inverter.
  • Carried the project from permit set to permission to operate in six weeks.

System specifications

System5.1 kW AC-CEC
ServiceUnderground
ModulesCanadian Solar CS1H-320MS, 320 W
InverterSolarEdge HD-Wave, wall mounted
RoofComposition shingle, two-storey house
Roof wiringCollected and bonded in a roof junction box
Utility / AHJLADWP / LADBS

Is your project like this one?

  • Your street has no power poles and you want to know whether that complicates solar.
  • You want a single string inverter rather than microinverters.
  • You want to know what a job looks like when nothing goes wrong.
  • You are being asked for a utility site visit and do not know why.
  • The utility has asked for a site visit and you want to know what it is for.

Cali Energy in Northridge

Northridge is inside City of Los Angeles boundaries: permits run through LADBS, interconnection through LADWP.

The newer tracts on the hill side of Northridge were built with the service underground, which changes where the utility looks when it comes to set the meter.

This installation is on the Northridge projects page alongside the others, and what the work covers is set out on the Northridge service area page.

Frequently asked questions

Does an underground service change the solar installation?

Not on the roof. It shapes the ground-level part: the utility's site visit, where the meter sits and how the new connection reaches it. On this project the service is recorded as underground on the utility's own work request.

Why does the utility need a site visit?

To see the existing service before committing to the connection. On this project the visit was requested and attended, and the four progress notices followed two days later.

What is the roof junction box for?

It is where the array wiring is collected and bonded before it runs down the conduit to the inverter. On this roof it sits at the top of the array.

How long did this project take?

Six weeks from the permit set arriving to permission to operate, with the proposals issued two months before that.

Do you quote more than one option?

On this house the owner had two proposals in January before anything was drawn. We quote more than one where the roof supports more than one sensible answer.

Does Cali Energy work on underground-served houses in Northridge?

Yes. Cali Energy holds B, C-10 and C-39 classifications under CSLB #1032379.

What this would look like on your roof

Every number on this page came off a real job in Northridge, CA — not a brochure. Tell us your utility, your roof and what your bill looks like now, and we will model your own version of it before you commit to anything.

Or call +1 (323) 844-7777 · Cali Energy, Northridge · CSLB #1032379 (B, C-10, C-39) — design, permits, install and electrical under one licensed contractor.

Related

This timeline reflects this property and this permitting path. Updated September 2026.