Winnetka, CA · September – December 2025 · LADWP / LADBS

One house. Two work requests. Two meter spots.

A 4.73 kilowatt DC system, 3.68 kilowatts AC-CEC, on a Winnetka house that also needed its service panel and service replaced. Those are two different jobs at the utility, and they do not travel together.

A service panel replacement and a solar interconnection are separate work requests at LADWP, handled by different groups. Each gets its own representative, its own meter spot and its own conditions — and the building department reviews them as separate permits.

Black solar modules across a composition shingle roof, Winnetka
The finished array on the main roof plane.

At a glance

DC System
4.73 kW
CEC-AC rating
3.68 kW
Modules
11 × URECO 430 W
Inverters
Enphase IQ8A
Service
200 A main breaker
Utility work requests
Two — service and solar
Permits
Panel upgrade and solar
Utility / AHJ
LADWP / LADBS

The story

Eleven URECO 430-watt modules, 4.73 kilowatts DC and a CEC-AC rating of 3.68 kilowatts, on IronRidge racking over a composition shingle roof. Each module has its own Enphase IQ8A microinverter. That part of the job is ordinary. What made this project worth writing down is what happened at the utility.

The house needed its main service panel replaced as well as the array installed. At LADWP those are not one job. The panel replacement went through Valley Service Planning on its own work request; the solar interconnection went through the PV Interconnections Group on a different one. Different groups, different representatives, different meter spots.

Open wall cavity with a conduit riser before the wall is closed, Winnetka
The riser in the open wall — the stage the utility asked to inspect before anything was closed up.

The service side moved first, and then stopped. LADWP publishes a window of five to fifteen business days for a meter spot visit to be assigned. On this project that window had passed with nothing scheduled, and the assigned representative's voicemail said he would be back in a month. We wrote to the department mailbox, confirmed that these were panel jobs rather than solar ones, and a second representative locked the dates. The meter spot arrived the same day.

It came with conditions, and they are the kind worth knowing before the wall is framed. The new meter panel had to go in the same position as the existing one or to the right of it. It could not sit directly above the crawl space entrance. And if a recessed panel and riser were used, the utility had to inspect the riser bracing before the walls were closed up — not after.

Open electrical panel with new wiring, Winnetka
The panel side of the work.

With the service settled, the interconnection application for the array went in, and the PV group issued its own meter spot for it. Two work requests, two meter spots, one house.

Both permits — the panel upgrade and the solar — were inspected in a single video slot under the building department's virtual inspection program. Taking part in that program means signing a participation agreement, which we did the day before. The same agreement prohibits recording the inspection, which is why there is no video of it.

Solar array on a shingle roof seen from the ridge, Winnetka
The array from the ridge.

The building department released the installation on the seventeenth of November, the utility completed its interconnection review the same day, and permission to operate came through on the third of December.

How it ran

10 September 2025Meter spot requested for the service panel replacement
7 October 2025Fifteen business days gone, no meter spot; escalated to the department
8 October 2025Dates locked and the meter spot issued, with its conditions
27 October 2025Interconnection application filed for the array; utility fees paid
31 October 2025Inspection requested for both permits
3 November 2025Virtual inspection participation agreement signed for both permits
3–4 November 2025Virtual inspection of both permits by the building department
4 November 2025Utility representative approval of the interconnection
17 November 2025Building department release; interconnection review completed
3 December 2025Permission to operate

The calendar covers two parallel utility work requests — one for the service panel, one for the solar — and the building department review of both permits.

What we did

  • Ran the service panel replacement and the solar interconnection as the two separate utility work requests they are.
  • Escalated a meter spot that had passed fifteen business days with no response, and got it issued the same day.
  • Built to the meter spot conditions: position relative to the existing panel, clearance of the crawl space entrance, riser bracing inspected before the walls closed.
  • Installed eleven modules on IronRidge racking, each on its own microinverter.
  • Signed the virtual inspection participation agreement and put both permits through one video slot.
  • Carried the project through building department release to permission to operate.

System specifications

DC system4.73 kW
CEC-AC rating3.68 kW
Modules11 × URECO 430 W
InvertersEnphase IQ8A-72-2-US, one per module
RackingIronRidge
RoofComposition shingle
BuildingTwo story, construction type V-B
Service1φ 3-wire 120/240 V; 200 A main breaker
Utility work requestsSeparate requests for the service panel and the solar
PermitsPanel upgrade and solar, inspected in one virtual slot
BatteryNone
Utility / AHJLADWP / LADBS

Is your project like this one?

  • Your house needs a new service panel as well as solar.
  • You have been told the utility is handling it and nothing is moving.
  • You are framing walls and nobody has told you what the utility needs to see first.
  • You want to know why there are two work request numbers on one project.
  • Your Winnetka property is served by LADWP, while permits are handled by LADBS.

Cali Energy in Winnetka

Winnetka is inside City of Los Angeles boundaries: permits run through LADBS, interconnection through LADWP.

Houses here are old enough that the service panel usually comes up in the same conversation as the array.

This installation is on the Winnetka projects page alongside the others, and what the work covers is set out on the Winnetka service area page.

Frequently asked questions

Do a panel upgrade and solar go through the utility together?

No. On this house they were two separate LADWP work requests: the service panel replacement through Valley Service Planning and the solar interconnection through the PV Interconnections Group. Each had its own representative and its own meter spot, and each carried its own building department permit.

What is a meter spot and what does it decide?

It is the utility's written approval of where the meter panel goes, and it carries conditions. On this project it required the new panel to sit in the same position as the existing one or to the right of it, kept it clear of the crawl space entrance, and required the utility to inspect the riser bracing before the walls were closed up.

How long should a meter spot take?

LADWP publishes a window of five to fifteen business days for the visit to be assigned. On this project that window had passed with nothing scheduled and the assigned representative was away, so we wrote to the department mailbox; a second representative picked it up and the meter spot was issued that day.

Can two permits be inspected in one visit?

They were here. The panel upgrade and the solar were both covered in a single slot under the building department's virtual inspection program, which is a LADBS program and separate from the utility's own approval. Taking part requires signing a participation agreement first, and that agreement prohibits recording the inspection.

Does Cali Energy handle service panel work as well as solar in Winnetka?

Yes. Cali Energy holds B, C-10 and C-39 classifications under CSLB #1032379, which lets us carry the panel, the service and the array under one contractor. Winnetka is inside City of Los Angeles boundaries, so permits run through LADBS and interconnection through LADWP.

What this would look like on your roof

Every number on this page came off a real job in Winnetka, CA — not a brochure. Tell us your utility, your roof and what your bill looks like now, and we will model your own version of it before you commit to anything.