Santa Clarita, CA · July 2021 – December 2022 · Southern California Edison / City of Santa Clarita

Santa Clarita: the array did not go on the roof at all.

Posts in the ground, concrete around them, and a trench back to the house. Almost nothing about it is a roof job.

A ground-mounted array solves the problems a roof creates — orientation, shading, a covering that will need replacing — and introduces its own: foundations that have to be engineered and poured, posts set and cured before anything is framed, and a buried run back to the service that is its own scope of work. On this Santa Clarita project Cali Energy set the array on posts in concrete with an underground route to the house, and the schedule was governed by the concrete rather than the panels.

Steel posts set in concrete under a ground-mount frame with the trench still open, Santa Clarita
No roof. The schedule here was set by curing concrete.

At a glance

Mounting
Ground mount on posts set in concrete
Foundation
Poured in two scheduled windows in one day
Route to the house
Underground
What set the pace
Curing, not panels
Utility / AHJ
Southern California Edison / Santa Clarita

The story

Most of what is written about solar assumes a roof. This array did not use one, and the differences start before anything is delivered.

A roof gives you a structure that already exists, at an orientation you have to accept, over a covering that will eventually need replacing underneath your hardware. A ground mount gives you the opposite deal: you choose the orientation and the tilt exactly, nothing shades it but what you allow to grow, and no future re-roof will ever require taking it apart. In exchange you have to build the structure yourself, starting underground.

The foundations came first. Posts set into the ground with concrete around them, poured in two scheduled windows on the same day — late morning and mid afternoon — because a concrete order arrives when it arrives and a crew stands waiting if the sequence is wrong.

Conduit running along a block retaining wall from the array toward the house, Santa Clarita
The route back to the house is underground, and it is trenched before anything is energized.

That is the first thing that surprises people about ground mounts: the critical path is not the array. It is the concrete. The posts have to be set plumb and in line, and then the concrete has to cure before any load goes on it. Nothing about that can be compressed by working faster, and modules delivered early just sit somewhere.

Then the framing above it, which is closer to ordinary steelwork than to roof mounting: pipe and rail, set to a tilt somebody chose rather than a pitch somebody inherited.

Conduit turning down into the ground beside a concrete pad, Santa Clarita
Every foot of this is work a roof array never needs.

And then the part that does not exist on a roof job at all — getting the power back to the house. A ground array sits away from the building by definition, so the conductors run underground: a trench, conduit, backfill, and a route that has to avoid everything else already buried on the property. It is its own scope, its own work and its own risk, and on a large lot it can be the longest single run in the project.

Worth being clear about what that means for anybody weighing the two. A ground mount is not the cheap option. It costs a foundation and a trench that a roof array does not, and those are civil works rather than electrical ones. What it buys is orientation you actually chose, tilt set for the site rather than the builder's pitch, access for cleaning and service without a ladder, and independence from the life of a roof covering.

A closed enclosure on the retaining wall with conduit entering from both sides, Santa Clarita
The electrical gear sits out with the array, not on the house.

It also draws a different kind of scrutiny. This project went back for plan corrections after the array was standing: the first final never went ahead, the revised set took until late October to come back approved, the inspection in November did not pass, and the one that did was in the middle of December. On a structure built from scratch the paperwork is checking a structure, not a mounting method, and that is a slower read.

The final passed in the middle of December, and the array has been running on its own foundations ever since — no roof to re-cover under it, and nothing to take apart when one is.

Cali Energy built and connected this ground-mounted array in Santa Clarita.

How it ran

26 July 2021Concrete ordered for two windows on the Thursday; solar materials released behind it
29 July 2021Foundations poured
16 September 2021Posts set and framing erected
7 October 2021Underground route run back to the service
May 2022Final first booked
July 2022Installation complete; the final does not go ahead — corrections issued and the plans sent back for revision
27 October 2022Revised plans approved by the city
23 November 2022Final held and not passed
16 December 2022Re-inspection; final passed

Seventeen months from the pour to a passed final. The panels were never the slow part.

What we did

  • Sequenced the concrete before the equipment rather than the other way round.
  • Set the posts and let them cure before any load went on them.
  • Ran the connection underground rather than across the property.
  • Carried the revised plan set through the corrections and back to a passed final.

System specifications

MountingGround mount, posts set in concrete
StructurePipe and rail above the posts
Tilt and orientationChosen for the site, not inherited from a roof
ConnectionUnderground run back to the service
PermitCorrections after installation; three inspection dates
Utility / AHJSouthern California Edison / Santa Clarita

Is your project like this one?

  • Your roof faces the wrong way and your lot is large.
  • Your covering is near the end of its life and you do not want to move an array later.
  • You have been quoted for a ground mount and the price surprised you.
  • You want to know what a ground array actually involves.

Cali Energy in Santa Clarita

Santa Clarita is its own city in Los Angeles County, permitted through the City of Santa Clarita Building & Safety Division and interconnected through Southern California Edison. Lots here are large enough that the roof is not always the obvious place for an array.

This installation is on the Santa Clarita projects page alongside the others, and what the work covers is set out on the Santa Clarita service area page.

Frequently asked questions

Is a ground-mounted solar array cheaper than a roof one?

No. It adds a foundation and a buried run that a roof array does not need, and those are civil works rather than electrical ones. What it buys is chosen orientation and tilt, easy access, and independence from the life of a roof covering.

What sets the schedule on a ground mount?

The concrete. Posts have to be set plumb and in line and then cured before any load goes on them, and nothing about that can be compressed by working faster. Modules delivered ahead of the foundation simply wait.

How does a ground array connect to the house?

Underground, in most cases: a trench, conduit and backfill on a route that has to miss everything already buried on the lot. On a large property it can be the longest single run in the project and it is its own scope of work.

Does a ground mount need different permitting?

It is reviewed as a structure rather than as something fixed to an existing one, which is a different kind of scrutiny. On this project corrections were issued after the array was standing and the plans were revised to answer them.

Does Cali Energy build ground-mounted arrays in Santa Clarita?

Yes. Lots here are often large enough that the roof is not the obvious place for an array. Projects are permitted through the City of Santa Clarita Building & Safety Division and interconnected through Southern California Edison.

What this would look like on your roof

Every number above came off a real job in Santa Clarita, CA — not a brochure. Tell us your utility, your roof and what your bill looks like now, and we will model your own version of it before you commit to anything.

Or call +1 (323) 844-7777 · Cali Energy, Northridge · CSLB #1032379 (B, C-10, C-39) — design, permits, install and electrical under one licensed contractor.

Related

This timeline reflects this property and this permitting path. Updated September 2026.