Hollywood Hills, CA · April 2022 – December 2023 · LADWP / LADBS

The inspector sent it back to plan check.

An inspection is meant to end in a signature. This one ended with the whole system being sent for drawings, over a disconnect that was not there.

The Los Angeles Fire Department's Requirement 96 governs rooftop photovoltaic systems, including where disconnecting means have to be and how conductors run between service equipment and sub panels. On this Hollywood Hills house the conductors ran from the meter socket to a sub panel in the garage with no disconnect between them and no overcurrent protection on that run. Because the installed arrangement did not meet the requirement, the inspector could not sign it off in the field — it had to go through plan check with the site conditions drawn. Cali Energy took this 29-module array in the Hollywood Hills, Los Angeles through that plan check and the corrections that followed it.

Conduit risers and a service head against a block wall beside a hillside house, Hollywood Hills, Los Angeles
The run between buildings is where this project turned.

At a glance

Array
29 modules, one inverter per module
Triggered by
Fire department requirement for rooftop photovoltaic systems
The issue
Unfused conductors, meter socket to garage sub panel, no disconnect
Inverters
Module-level, not a central inverter
Outcome
Field sign-off refused; full plan check required
Utility / AHJ
LADWP / LADBS

The story

Most corrections are a line on a card. This one was a sentence from a mechanical inspector that changed the shape of the whole project: the system would have to go to plan check, because what was installed did not meet the fire department's requirement for rooftop photovoltaic systems.

The specific objection was precise and worth understanding, because it recurs on houses with detached garages. The conductors ran from the meter socket to a sub panel in the garage. There was no disconnecting means between them, and that run carried no overcurrent protection — unfused conductors, in the language of the correction. The requirement is not silent about that arrangement, and an inspector cannot sign off something the requirement does not permit, however well it is built.

We put the obvious question back. The system is on module-level inverters rather than a central inverter, and the alternating-current disconnect and the meter are within three feet of each other. On a great many systems that combination answers the question entirely.

Conduit laid in an open trench alongside a wall, Hollywood Hills, Los Angeles
Site conditions, shown rather than described.

It did not answer it here, and the reply was one line: what is installed on site does not meet the requirement. That is the part worth sitting with. Module-level inverters change where the direct-current side ends and what has to be isolated on the roof. They do not change what happens between the meter and a sub panel in another building. Those are different problems, and an answer to one is not an answer to the other.

So the system went to plan check, with an instruction attached: show the site conditions. Not a typical set — the actual arrangement, including the run with no disconnect on it, drawn as it exists. A plan checker cannot approve a remedy for a condition that is not on the drawing.

An alternating-current disconnect mounted on a timber wall with conduit entering from below, Hollywood Hills, Los Angeles
A disconnect where the correction said there should be one.

The revised set came back ten days later, and reviewing it produced its own list. The existing sub panel had dropped off the drawing between versions and had to go back on. The single-line diagram described the service as existing where the scope called for a new one — a one-letter difference on a drawing that decides which service the whole design is built around. And the main breaker had been de-rated on the new set with nothing in the scope calling for it.

None of those three would have stopped the array working. All three would have stopped the plan check, and the second of them would have been discovered at the final, with the panel already on the wall.

The project ran on into the following year, with a formal correction notice in the late summer of 2023 and the file closing out that November. Twenty months on a question that started as a disconnect between two buildings.

A combiner enclosure mounted on an exterior wall with its rapid-shutdown and warning labels, Hollywood Hills, Los Angeles
Closed, labeled, and drawn as it actually sits.

What to take from it. If your house has a detached garage with a sub panel, ask early where the disconnect between the meter and that sub panel is and whether the run is protected. And if you are told a correction can be resolved in the field, ask whether it is a code question or a fire-department requirement — because the second kind ends in drawings, and the drawings have their own queue.

Cali Energy carried this Hollywood Hills project in Los Angeles through the plan check the inspection triggered, and the array was commissioned once the corrections cleared.

How it ran

19 April 2022Inspection; mechanical inspector refuses field sign-off and requires plan check
19 April 2022Question put back — module-level inverters, disconnect and meter within three feet
19 April 2022Inspector holds: the installed arrangement does not meet the requirement
29 April 2022Revised plan set issued for review
2 May 2022Review returns three items — missing sub panel, service described as existing rather than new, unexplained de-rate
August – September 2023Formal correction notice worked through
November 2023Corrections cleared

Twenty months from the first correction to the last message, and the trigger was a run of conductors between two buildings.

What we did

  • Put the microinverter argument to the inspector rather than assuming it applied.
  • Took the system to plan check with the site conditions drawn as they actually were.
  • Reviewed the revised set before it went for stamping and returned three corrections.
  • Carried the formal correction notice through to a closed file.

System specifications

Array29 modules, 29 module-level inverters
ObjectionNo disconnecting means between meter socket and garage sub panel
ConductorsUnfused on that run
Resolution routePlan check with site conditions drawn as they exist
Drawing errors caught in reviewMissing sub panel; existing-versus-new service; unexplained main breaker de-rate
Utility / AHJLADWP / LADBS

Is your project like this one?

  • Your house has a detached garage with its own sub panel.
  • An inspector has told you the system needs to go to plan check.
  • You have been told microinverters solve a disconnect question.
  • Conductors run between your meter and another building with nothing in between.
  • A revised plan set came back and you are not sure what to check on it.

Cali Energy in Hollywood Hills

The Hollywood Hills are inside City of Los Angeles boundaries, permitted through LADBS and interconnected through LADWP, with the fire department's own requirement applying to every rooftop array. On a hillside house with a detached garage, the run between the meter and the sub panel is where that requirement usually bites.

This installation is on the Los Angeles projects page alongside the others, and what the work covers is set out on the Los Angeles service area page.

Frequently asked questions

Why would an inspector send a finished system to plan check?

Because a field inspection can only sign off what the approved drawings and the applicable requirements allow. If the installed arrangement does not meet a requirement — here the fire department's rule for rooftop photovoltaic systems — there is nothing the inspector can approve on site. The remedy has to be drawn, reviewed and approved before it can be inspected.

Do microinverters remove the need for a disconnect?

Not in general. Module-level inverters change where the direct-current side ends and what has to be isolated on the roof, which answers some disconnect questions. They say nothing about the run between the meter and a sub panel in another building. On this project that distinction was exactly the point, and the microinverter argument did not apply.

What does 'unfused conductors' mean on a correction?

That a run of conductors has no overcurrent protection at its supply end. Between a meter socket and a sub panel in a detached garage that is a familiar arrangement and a familiar problem: nothing between the two buildings can clear a fault on that run, and there is no means of disconnecting it.

What should I check on a revised plan set?

That everything on the previous set is still there, that the service is described as existing or new to match the actual scope, and that nothing has been de-rated without a reason in the scope. On this project all three came up on one revision. None would have stopped the array working; all three would have stopped the plan check.

Does Cali Energy work on Hollywood Hills houses with detached garages?

Yes, and the sub panel in the garage is one of the recurring questions in this part of Los Angeles. Cali Energy looks at the run between the meter and any detached structure before the design is finished, because a missing disconnect on that run is found at the inspection and fixed in plan check, which is the expensive order to do it in.

What this would look like on your roof

Every number above came off a real job in Hollywood Hills, CA — not a brochure. Tell us your utility, your roof and what your bill looks like now, and we will model your own version of it before you commit to anything.

Or call +1 (323) 844-7777 · Cali Energy, Northridge · CSLB #1032379 (B, C-10, C-39) — design, permits, install and electrical under one licensed contractor.

Related

This timeline reflects this property and this permitting path. Updated September 2026.